Project Portfolio

REYTEC CONSTRUCTION RESOURCES PROJECT PORTFOLIO

MIDTOWN REDEVELOPMENT AUTHORITY - McGowen St. Reconstruction (Smith to Hamilton)

Reytec is the Prime Contractor to the Midtown Redevelopment Authority and is responsible for the traffic control, street lighting, pavement markings, pollution prevention, site work/landscaping, demolition of existing concrete/asphalt paving (curbs, sidewalks, storm sewer), install concrete paving stamped concrete sidewalks, curbs, install sanitary sewer, waterline, storm sewer, 18,000 square yards of 10” concrete paving, and installation of new traffic signals. The sidewalks for this project also required decorative brick pavers to be installed throughout the length of the project. The traffic signaling was of a different standard design to complement the existing signal in the Midtown area.

Contract Amount: $5,423,241.00